Current:Home > reviewsMassachusetts budget approval allows utilities to recoup added cost of hydropower corridor -BeyondProfit Compass
Massachusetts budget approval allows utilities to recoup added cost of hydropower corridor
View
Date:2025-04-16 18:54:27
PORTLAND, Maine (AP) — A budget signed by Massachusetts Gov. Maura Healey this week will allow utilities to raise rates to make up for hundreds of millions of dollars in additional costs to complete a transmission line to bring Canadian hydropower to the New England electricity grid.
The head of Central Maine Power Co.'s corporate parent Avangrid has said the cost of the $1 billion project grew to $1.5 billion as litigation delayed construction and inflation caused prices to creep upward.
Legislation included the supplemental budget adopted Monday allows transmission service agreements to be renegotiated and additional costs to be passed along to Massachusetts ratepayers to cover the added costs.
Avangrid provided the increased costs to Massachusetts’ electricity distribution companies to adjust the rate in the parties’ transmission services agreements, which would be subject to Department of Public Utilities review and approval, Avangrid spokesperson Leo Rosales said in a statement Tuesday.
He praised Healey and lawmakers for taking action to “deliver this critical project and needed clean power to benefit the entire New England region.”
Avangrid partnered with Hydro-Quebec on the New England Clean Energy Connect to supply 1,200 megawatts of hydropower to meet green energy goals in Massachusetts. That would be enough electricity to power about a million homes.
The 145-mile (233-kilometer) transmission line will stretch from Lewiston, Maine, to the Canadian border.
It received all regulatory approvals but was plagued by delays, litigation and a referendum in which https://apnews.com/article/election-2021-maine-hydropower-line-54dea1a948e9fc57a667280707cddeb7
It was allowed to move forward after a Maine jury concluded that the developers had a constitutional right to proceed despite the referendum.
Construction resumed in August on a transmission hub that’s critical to the project in Lewiston. But it’s unclear when other work will restart.
Workers had already begun removing trees and setting utility poles on a disputed portion of the project, a new 53-mile (85-kilometer) section cut through the woods in western Maine, before the project was put on hold.
The project was envisioned to meet Massachusetts’ clean energy goals, and the cost is fully borne by ratepayers in that state.
However, supporters say electricity would lower energy costs across New England as well as reduce carbon pollution.
veryGood! (2)
Related
- Are Instagram, Facebook and WhatsApp down? Meta says most issues resolved after outages
- Iran executes 4 men convicted of planning sabotage and alleged links with Israel’s Mossad spy agency
- Iran launches 3 satellites into space that are part of a Western-criticized program as tensions rise
- High-ranking Orthodox prelate warns against spread of antisemitism by religious officials
- Could your smelly farts help science?
- 'Vanderpump Rules,' 'Scandoval' and a fight that never ends
- Where is Super Bowl 58? Allegiant Stadium in Las Vegas is set to host Chiefs vs. 49ers
- Eminem goes after Benzino in new Lyrical Lemonade track, rekindles longtime feud
- US wholesale inflation accelerated in November in sign that some price pressures remain elevated
- 2 accused of racing held for trial in crash with school van that killed a teen and injured others
Ranking
- 2025 'Doomsday Clock': This is how close we are to self
- Former NHL player accused of sexual assault turns himself in to Ontario police
- Yemen’s Houthi rebels say they attacked a US warship without evidence. An American official rejects the claim
- Somali pirates suspected of hijacking a Sri Lankan fishing boat and abducting its 6 crew
- EU countries double down on a halt to Syrian asylum claims but will not yet send people back
- Oklahoma trooper violently thrown to the ground as vehicle on interstate hits one he’d pulled over
- Dakota Johnson's 'SNL' opening monologue crashed by Justin Timberlake and Jimmy Fallon
- Jannik Sinner establishes himself as legitimate star with comeback win at Australian Open
Recommendation
Where will Elmo go? HBO moves away from 'Sesame Street'
Kate Middleton Released From Hospital After Abdominal Surgery
Russian election officials register Putin to run in March election he’s all but certain to win
Ravens QB Lamar Jackson can't hide his disappointment after stumbling against Chiefs
Kylie Jenner Shows Off Sweet Notes From Nieces Dream Kardashian & Chicago West
Ex-Philippines leader Duterte assails Marcos, accusing him of plotting to expand grip on power
2 are in custody after baby girl is found abandoned behind dumpsters in Mississippi
Country music star Chris Young cleared of all charges after arrest in Nashville bar